Project

Mornington Battery

PROJECT STATUS
Operational
Mornington Battery

The Mornington Battery Energy Storage System, developed by Valent Energy, is a 240-megawatt / 480-megawatt hour battery located in Victoria's Mornington Peninsula, adjacent to the existing Tyabb Terminal Station.

Key Dates

Apr 2023 Construction Commencement
Nov 2025 Construction Completion

Procurement

Procuring Agency: Valent Energy
Successful Tenderer: Downer

PROJECT HISTORY

Jul 2021 The Mornington BESS project was placed on Public Exhibition for review.
Jan 2022 The Mornington Peninsula Battery project received development approval from the Victorian Government.
Sep 2025 The project was awarded a Capacity Investment Scheme Agreement as part of the Capacity Investment Scheme Tender Round Three.
Nov 2025 The project reached energisation and commenced operations.
Sector
Energy
Procurement approach
Balance of Plant |
Location
Victoria |
Resources
Project website
Mornington Battery