Search the Infrastructure Pipeline

Analyse the
Infrastructure Pipeline


Our dynamic charts make it easy to get an up-to-date view of the Australia and New Zealand Infrastructure Pipeline. Pick one of the charts and filter by location, sector, status and procurement approach to explore the data behind the pipeline.

Infrastructure Pipeline chart

Recent Updates

Project Updated   23 Sep

The Federal Government, through the High Speed Rail Authority, is progressing the delivery of a high-speed rail network between Melbourne and Brisbane via Sydney.

The first stage of the network connects Newcastle with Western Sydney Airport via Sydney Central. The preferred route includes stations at Newcastle, Lake Macquarie, Central Coast, Sydney Central, Parramatta, and Western Sydney Airport. Stage 1 will be delivered across three phases:

  • Stage 1A – Newcastle to the Central Coast: construction proposed to commence 2027, operational by 2037
  • Stage 1B – Central Coast to Sydney Central: construction proposed to commence 2027, operational by 2039
  • Stage 1C – Sydney Central to Western Sydney Airport: construction proposed to commence 2034, operational by 2043

The estimated P90 project cost is $61.2 billion for Stages 1A and 1B, and $32.4 billion for Stage 1C. 

The project scope includes:

  • a dedicated high-speed rail alignment between Newcastle and Western Sydney Airport
  • new stations at Newcastle, Lake Macquarie, Central Coast, Sydney Central, Parramatta, and Western Sydney Airport
  • improvements to integrated transport networks
  • trains capable of speeds greater than 250 km/h
  • stabling, maintenance, rail systems and power upgrades, and
  • corridor protection for future connections to Brisbane and Melbourne
STATUS: Detailed Planning
Project Updated   23 Sep
part of Sydney Ring

The Hunter Transmission project is the 110-kilometre northern section of the Sydney Ring. It involves building a new above-ground 500 kilovolt (kV) transmission line between Bayswater and Eraring in the Hunter region to connect the State’s existing 500 kV transmission lines.

The HTP will close the northern loop between existing transmission lines: 

  • two 500-kV transmission lines in the east, which connect the power stations on the Central Coast (Eraring and Vales Point) via Eraring to the Kemps Creek substation in Western Sydney, and 
  • two 500 kV transmission lines in the west, which connect Bayswater Power Station in the Upper Hunter to Mt Piper Power Station near Lithgow, and Bannaby substation in the Southern Tablelands.

The Hunter Transmission Project's preliminary corridor is divided into three sections: 

  • HTP North – Bayswater to Broke. Most of the northern section of the preliminary corridor runs through the Hunter Valley Operations Mining Complex, industrial land and Department of Defence land. 
  • HTP Central – Pokolbin to Corrabare. Much of the central section of the preliminary corridor runs through the Pokolbin and Corrabare State forests.
  • HTP South – Olney to Eraring. The southern section of the preliminary corridor runs mostly through the Olney State Forest and includes a substation in the forest.

The project includes delivery of two new substations at Bayswater and Olney and upgrades to the existing Bayswater and Eraring Substations.

Design and construction of this project will be procured via a competitive, open market tender process.

STATUS: Under Procurement
Project Updated   20 Sep

The Gippsland Offshore Wind Transmission Project will support the connection of offshore wind infrastructure in the Gippsland Offshore Wind Zone to the mainland grid. The project will run from a new connection hub on the mainland near the Gippsland coast, which will service offshore wind farm connections, to a grid connection point near Loy Yang Power Station. 

The proposed project comprises the development, construction and operation of approximately:

  • 55 kilometres of 500-kilovolt transmission lines
  • an onshore connection hub, including high-voltage substation plant and equipment, and
  • a grid connection substation near the Loy Yang Power Station.

The project was formerly known as the Greater Gippsland Transmission Project.

STATUS: Under Procurement
Status Changed   07 Sep
part of Suburban Rail Loop

The first stage of the Suburban Rail Loop – SRL East – is a fully-tunnelled 26-kilometre metro corridor between Cheltenham in the South and Box Hill in the North. The line will include six stations, including new interchanges with existing heavy rail stations at Cheltenham, Clayton, Glen Waverley and Box Hill, with new stations at Monash and Burwood.

The Suburban Rail Loop Authority has separated SRL East into seven packages. Included in the scope of Works Package D is:

  • 10 kilometres of twin tunnelling and cross passages between Glen Waverley and Box Hill
  • Burwood and Glen Waverley station box excavations, including temporary retaining structures, and 
  • an intervention shaft structure.
STATUS: Under Delivery
Project Updated   04 Sep

The Orana Battery Energy Storage System, developed by Akaysha Energy, involved the construction and operation of a 415-megawatt (MW) / 1,660-megawatt hour (MWh) lithium-ion battery energy storage system (BESS) and ancillary infrastructure.

The Project is located within the Central-West Orana Renewable Energy Zone, approximately two kilometres north-east of Wellington within the Dubbo Local Government Area.

STATUS: Operational
Status Changed   03 Sep

The Mortlake Battery project is a proposed 300 megawatt (MW) / 650 megawatt hour (MWh) battery energy storage project being developed by Origin Energy. The battery is to be co-located at the Mortlake Power Station in Victoria, where Origin operates a 566 MW gas-fired generator.

This project is located within the Victorian South-West REZ V4 region. The battery will be connected to the 500 kilovolt network that runs through the power station.

Construction of the Mortlake battery will take place in three phases:

  • site preparation and civil works
  • component delivery and installation, and
  • commissioning and demobilisation.
STATUS: Operational
Status Changed   02 Sep

The WWSP will deliver a number of upgrades to Auckland's water supply. The full scope of the programme comprises: 

  • a new 150-MLD water treatment plant
  • a new 50-megalitre reservoir at Pukekohe West
  • a 50-kilometre pipeline, including the crossing of the Manukau Harbour, and
  • three additional pumps and sand separators for the raw water intake.
STATUS: Under Procurement
Status Changed   31 Aug

Gawara Baya Wind Farm is being developed by Windlab in North Queensland. The project would see the installation of 69 wind turbines, generating a total capacity of 400 megawatts (MW). 

The project is to be located 65 kilometres southwest of Ingham, Queensland. The project was formerly known as the Upper Burdekin Wind Farm.

 

 

STATUS: Awarded

Learn how to make the most of ANZIP


Welcome to the Australian and New Zealand Infrastructure Pipeline platform, a search tool for infrastructure projects. The Beta version offers new exciting features as well as improved popular features like Map view. Simply go to 'Search' in the menu bar to access the map.

See more tips

Partners

SIGN IN TO ANZIP AND SUBSCRIBE TO THE PIPELINE REPORT


Sign in to make the most of ANZIP. Subscribe to the Pipeline Report, Infrastructure Partnership's monthly analysis of Pipeline data and project movements, review past editions of the report and keep track of your Saved Projects.

Sign up
The Pipeline Report
June edition
Added to ANZIP from FY2022-23 Budgets