The Bellambi Heights Battery Energy Storage system, proposed by Vena Energy, is a 408-megawatt (MW) / 816-megawatt hour (MWh) battery to be located in Beryl NSW, approximately 85 kilometres east of Dubbo.
The project will be delivered in two stages, each providing 204 MW and 408 MWh of capacity and storage. The project site is located within the Central West Orana REZ.
Key Dates
| Mar 2022 | Project Announcement |
| Mar 2026 | Construction Commencement |
Procurement
| Procuring Agency: | Vena Energy |
| Related contracts: |
PROJECT HISTORY
| Mar 2022 | A Scoping Report and request for the Secretary's Environmental Assessment Requirements (SEARs) were published for the project. |
| Apr 2023 | SEARs were granted for the project. |
| Jul 2023 | The Environmental Impact Statement was published and placed on public exhibition. |
| May 2024 | The NSW Government granted planning approval for the project. |
| Mar 2026 | Vena Energy announced that construction had commenced on the project. Additionally, Ashurst announced that it had advised Vena Group on a Revenue Share Agreement with InCommodities for the Bellambi Heights BESS. |
Sector
Energy
Procurement approach
Engineering, Procurement and Construction (EPC) |
Location
New South Wales |