Project

Carmody's Hill Wind Farm

PROJECT STATUS
Under Delivery
Carmody's Hill Wind Farm

Carmody's Hill Wind Farm is a wind generation project to be located in the Mid North region of South Australia, approximately 7 kilometres of Georgetown.

The scope of works includes: 

  • 42 wind turbines for a total capacity of 256 megawatts (MW)
  • option of battery energy storage system with 123 MW capacity (no duration has been specified), and
  • 12.8 kilometres of 275 kilovolt (kV) transmission line connecting into the existing Davenport to Brinkworth 275kV line.

The project is being co-developed by Aula Energy and Renewable Project Services.

Key Dates

Dec 2025 Contract Award
Mar 2026 Construction Commencement

Financing

;
Clean Energy Finance Corporation

Procurement

Procuring Agency: Aula Energy
Successful Tenderer: DT Infrastructure
Related contracts:
Construction Managment Services
Successful Tenderer - GHD

PPA
Successful Tenderer - Snowy Hydro

PROJECT HISTORY

Feb 2025 Aula Energy announced that the Early Contractor Involvement phase commenced.
Oct 2025 The project was awarded a Capacity Investment Scheme Agreement as part of the Capacity Investment Scheme Tender Round Four.
Nov 2025 The project received approval for its Negotiated Generator Performance Standards (NER 5.3.4A) from ElectraNet and AEMO.
Nov 2025 Aula Energy and Snowy Hydro have signed a 15-year Power Purchase Agreement (PPA) for 256-megawatt Carmody's Hill Wind Farm in South Australia's Mid North. Under the PPA, Snowy Hydro will procure energy from 120 MW of the project’s capacity. The proposed project is subject to financial close.
Dec 2025 Aula Energy awarded the main works Balance of Plant contract to DT Infrastructure, following the completion of financial close and an ECI process. Aula Energy provided an updated timeline for the project, with main works expected to commence in early 2026, with operations expected to begin in late 2028.
Dec 2025 Aula Energy awarded a contract for Construction Managment Services to GHD. Contracted services include contractor coordination, compliance, community and stakeholder engagement, and broader project management services.
2026 Construction commenced on the project.
Estimated Total Cost
(2025)
Sector
Energy
Procurement approach
Balance of Plant |
Location
South Australia |
Resources
Infrastructure agency resources
ECI Commenced
Tender notices
CIS Tender Round 4
Project pages
Project page