Cattle Creek Wind Farm is a proposed 972 MW facility to be located 110km west of Toowoomba, QLD. The scope of the project will include 135 turbines and a 450MW BESS and is being delivered by RWE Renewables Australia.
Key Dates
| May 2024 | Project Announcement |
| 2028 | Expected Construction Commencement |
| 2030 | Expected Construction Completion |
Procurement
| Procuring Agency: | RWE |
PROJECT HISTORY
| Apr 2025 | The project was referred to the EPBC Portal for Federal environmental assessment. |
| May 2025 | The Federal Department of Climate Change, Energy, the Environment and Water determined that the project was a controlled action and required assessment under the EPBC Act. |
| Jul 2026 | The Federal Department of Industry, Science and Resources approved the projects' Australian Industry Participation Plan. |
| Aug 2026 | A development application was submitted to the Queensland State Assessment and Referral Agency (SARA). |
Sector
Energy
Procurement approach
Design and Construct (D&C) |
Location
Queensland |