The Eyre Peninsula Desalination Plant is a proposed desalination plant located near Billy Lights Point, South Australia.
The project includes construction of a reverse osmosis seawater desalination plant and supporting infrastructure. The facility will have an annual capacity of 5.3 gigalitres and will service the water-vulnerable communities on the Eyre Peninsula.
Key Dates
| May 2023 | EOIs Open |
| Nov 2023 | Contract Award |
| Jul 2025 | Construction Commencement |
| Jun 2027 | Expected Construction Completion |
Procurement
| Procuring Agency: | SA Water |
| Successful Tenderer: | ACCIONA |
| Procurement note: | The contract is being delivered through an ECI process. |
PROJECT HISTORY
| Mar 2023 | The South Australian Government accepted the recommendation from SA Water to select Billy Lights Point as the preferred site for the Eyre Peninsula Desalination Plant. |
| May 2023 | SA Water commenced an Expressions of Interest process for Design and Early Contractor Involvement. |
| Jun 2023 | The 2023-24 SA Budget revealed a cost increase for the project to $330 million and pushed back the estimated completion date to March 2026. |
| Nov 2023 | SA Water announced that ACCIONA had been awarded the ECI contract for the delivery of the Eyre Peninsula Desalination Project. |
| Apr 2024 | Geotechnical investigation work commenced at the site to assist in the planning of construction. A construction completion estimate of mid-2026 was also announced. |
| May 2025 | ACCIONA announced that delivery had commenced on the structural, mechanical, and piping installation package for the project. |
| Jun 2025 | The 2025-26 South Australian Budget details SA Water’s capital commitments, including $155 million in FY2025-26 to the project. |
| Jul 2025 | SA Water confirmed that ACCIONA will be the main works contractor to deliver the project, following participation in an Early Contractor Involvement process. It has also confirmed an increase in project cost to $470 million and a revised completion date of late 2026. |
| Aug 2025 | Main works commenced on the project. |
| Oct 2026 | SA Water announced an updated completion date for the project, with the plant expected to commence operations by June 2027. |
Estimated Total Cost
(2025)
Sector
Water & Sewerage
Procurement approach
Traditional Procurement |
Location
South Australia |
Resources
Media releases
2023/03/10 - Site Selection - SA Water2023/03/9 - Site Selection - SA Government
2023/05/02
2023/11/1 - Contract Award
2024/04 - Geotechnical Investigations
2024/04
2025/07/25 - Main works contract, revised cost
2025/08/01 - August Update
2026/05/26 - Structural Package Commencement
2026/10/16 - Updated completion timeframe