Project

Goyder Renewables Zone

PROJECT STATUS
Under Delivery
Goyder Renewables Zone

Goyder Renewables Zone is a hybrid renewable energy development proposed for the area around Burra, in the Goyder region of South Australia. The Zone includes two separate projects: Goyder South and Goyder North.

Goyder South comprises multiple stages:

  • Stage 1A: 209 megwatts of wind generation / 38 turbines (operational)
  • Stage 1B: 203 megawatts of wind generation / 37 turbines (operational)
  • Stage 2/3: Proposal for up to 600 megawatts of wind generation, 600 megawatts of solar generation and 900 megawatts / 1,800 megawatt hours of battery storage

Goyder North will comprise:

  • Goyder North Wind Farm
    • Stage One: 48 turbines with 346-MW capacity
  • Goyder North Battery
    • Stage One: 227 MW / 907 MWh
    • Stage Two: 227 MW / 907 MWh

Goyder North Wind Farm is approved to comprise a total of 99 wind turbines with a total capacity of appoximately 600 megawatts, and is expected to be delivered over two stages.

Key Dates

Jan 2022 Contract Award: Goyder South Stage One
Jul 2022 Construction Commencement: Goyder South Stage One
Oct 2025 Construction Completion: Goyder South Stage One

Financing

In February 2024, the Clean Energy Finance Corporation committed $102.4 million to Goyder South Stage 1B Wind Farm and the Blyth Battery in South Australia.

Procurement

Procuring Agency: Neoen
Successful Tenderer: Goyder South Wind Farm: GE Renewable Energy and Elecnor
Related contracts:
Power Purchase Agreement (Goyder South - Stage 1A)
Successful Tenderer - Flow Power, ACT Government

Power Purchase Agreement (Goyder South - Stage 1B)
Successful Tenderer - BHP for the Olympic Dam

PROJECT HISTORY

Jun 2020 Neoen submitted a Development Application for Goyder South to the South Australian Government for planning approval.
Aug 2020 Neoen released the Development Application for Goyder South for public exhibition.
Mar 2021 Goyder South received development approval from the South Australian Government, with up to 1,800 MW of wind and solar generation and 900 MW of battery storage approved.
Jan 2022 GE Renewable Energy was awarded the contract to deliver the 412 MW wind farm as part of Goyder South Stage One.
Jun 2022 Goyder South Stage 1A received Federal Government approval.
Jul 2022 Construction commenced on Goyder South Stage One.
Jul 2022 Goyder South Stage 1B received Federal Government approval.
Aug 2022 A 10-year power purchase agreement was signed with Flow Power for 40 megawatts of output under Goyder South Stage One.
Sep 2022 The overhead transmission line and substation has received Federal Government approval.
Dec 2022 Neoen has signed a 70 MW renewable energy baseload contract with BHP to supply power to its Olympic Dam operations in South Australia from July 2025. Output will come from Goyder South Stage One and the Blyth Battery.
Jan 2023 Neoen reached financial close on Stage 1A of Goyder South, underpinned by two power purchase agreements - a 14-year contract for 100 megawatts with the ACT Government and the 10-year agreement with Flower Power. It has been financed by a combination of equity provided by Neoen and debt facilities provided by a group of six lenders including ANZ, HSBC, Mizuho, Societe Generale, Sumitomo Mitsui Banking Corporation, and Westpac.
Dec 2023 The Goyder South Stage 1A and 1B Substation and Overhead Transmission Line have both been energised, connecting to the South Australian grid.
Feb 2024 Goyder South Stage 1B reached financial close, as well as the 240 MW / 477 MWh Blyth Battery. The projects have been jointly financed by a combination of equity provided by Neoen and debt facilities from a group of five lenders including the Clean Energy Finance Corporation, KfW IPEX-Bank, ING, Mizuho and Westpac.
Oct 2025 Neoen has announced that the 412-megawatt Goyder South Wind Farm (comprising Stages 1A and 1B) is now operational.
Major Contract

Goyder North

PROJECT STATUS
Under Delivery
Goyder North

Goyder North is part of the Goyder Renewables Zone and comprises:

  • Goyder North Wind Farm
    • Stage One: 48 turbines with 346-MW capacity
  • Goyder North Battery
    • Stage One: 227 MW / 907 MWh
    • Stage Two: 227 MW / 907 MWh

The wind farm has Federal Government approval for up to 99 turbines and a total capacity of approximately 600 MW, and is expected to be delivered over two stages. The complete scope of Stage Two has not been confirmed.

Key Dates

Dec 2025 Construction commencement: Battery Stage One
Jul 2026 Construction commencement: Battery Stage Two
Oct 2026 Contract Award: Wind Farm Stage One
Oct 2026 Construction commencement: Wind Farm Stage One
2028 Expected construction completion: Battery
2029 Expected construction completion: Wind Farm Stage One

Procurement

Procuring Agency: Neoen
Successful Tenderer: Battery: UGL (Balance of Plant), Tesla (battery) Wind Farm Stage One: Vestas (wind turbine supply and installation); Downer transmission connection

PROJECT HISTORY

Dec 2024 The Federal Government announced that the Goyder North Stage One Wind Farm was awarded a Capacity Investment Scheme Agreement under Tender Round One.
Mar 2025 The Goyder North Wind Farm, as part of the Goyder Renewables Zone, was included in the Federal Government's inaugural Renewable Energy Priority List. The Priority List aims to provide coordinated support through Federal, state and territory regulatory and environmental approval processes on a case-by-case basis and provide a 'faster to yes, faster to no' approach to regulatory approvals.
Feb 2026 Goyder North received Federal Government approval under the Environment Protection and Biodiversity Conservation Act (Cth)1999.
Jul 2026 UGL was awarded the Balance of Plant contract to deliver Stage Two of Neoen’s Goyder Battery in South Australia, as part of Neoen’s Northern Goyder Renewables Zone. Stage Two has a capacity of 227 megawatt / 907 megawatt-hours, and matches Goyder Battery Stage One’s capacity, also under delivery by UGL. Site works for Stage Two are expected to commence in August, with the project anticipated to be operational in 2028.
Oct 2026 Neoen announced that contracts had been awarded and construction had commenced on Stage One of the Goyder North Wind Farm. Vestas was awarded the contract deliver the 346-megawatt wind farm, including supply of 48 turbines, and Downer was selected to design and construct the overhead transmission line and switching station to connect the project to the NEM.
Estimated Total Cost
(2023)
Sector
Energy
Procurement approach
Market Led Proposal |
Location
South Australia |
Resources
Project pages
Goyder North