Project

Gundary Solar Farm

PROJECT STATUS
Detailed Planning
Gundary Solar Farm

The Gundary Solar Farm, proposed by Lightsource BP, is a 400-megawatt (MW) solar generation project and 555-MW / 1,570-megawatt hour (MWh) battery. The project is expected to be located across 708 hectares of land in Gundary, NSW.

The scope of the works includes:

  • a 400-MW solar farm comprising approximately 740 solar panels
  • a 555-MW / 1,570-MWh Battery Energy Storage System
  • an onsite substation
  • a system of inverters and voltage step-up transformers, and
  • one switchyard.

Key Dates

Sep 2022 Project Announcement
2027 Expected Construction Commencement

Procurement

Procuring Agency: Lightsource BP

PROJECT HISTORY

Sep 2022 Lightsource BP submitted a Scoping Report and made a request for the Secretary's Environmental Assessment Requirements (SEARs) to the NSW Government. The proposed project includes a 400-megawatt (MW) solar farm and 200- to 400-MW / 400- to 800-MWh battery.
Nov 2022 The NSW Department of Planning and Environment issued the Secretary's Environmental Assessment Requirements for the project.
Nov 2024 The Environmental Impact Statement for the project was placed on public exhibition, closing on 12 December. Additionally, the EIS provided an updated construction cost of $650 million, and updated construction commencement date of Q1 2026. The EIS also provided an updated battery capacity of 555 megawatts / 1,570 megawatt hours.
Mar 2026 The March 2026 project update outlined an updated timeline for the project, with main works construction expected to start in late 2027.
May 2026 The project was invited to enter into a Capacity Investment Scheme Agreement as part of the Capacity Investment Scheme Tender Round Seven.
Estimated Total Cost
(2022)
Sector
Energy
Procurement approach
Other |
Location
New South Wales |
Resources
Project website
Lightsource BP
Government resources
Capacity Investment Scheme
Project pages
NSW Planning Portal