Hexham Straight Widening

PROJECT STATUS
Operational
Hexham Straight Widening

The Hexham Straight Widening will upgrade six kilometres of the Pacific Highway between the Newcastle Inner City Bypass and the Hexham Bridge.

The project's scope includes:

  • a six-kilometre upgrade of the Pacific Highway between the Newcastle Inner City Bypass and the Hexham Bridge
  • widening from dual carriageway to triple carriageway
  • demolition of the existing Ironbark bridge and construction of two new bridges at Ironbark Creek, and
  • utility relocations. 

Key Dates

Mar 2022 ROIs Open
May 2022 ROIs Close
Jul 2023 Construction Commencement
Feb 2026 Construction Completion
Feb 2026 Operations/Service Commencement

Funding contributions

The project is being funded as part of the broader M1 Extension to Raymond Terrace project. 

Procurement

Procuring Agency: Transport for NSW
Successful Tenderer: An Alliance of Georgiou, Daracon Contractors, and SMEC
Procurement note:

Registartions of Interest have only been opened to pre-qualified contractors.  

PROJECT HISTORY

Mar 2022 TfNSW opened Registrations of Interest for the project to pre-qualified contractors.
Dec 2022 An Alliance of Georgiou, Daracon Contractors, and SMEC was awarded the contract for the delivery of the Hexham Straight Widening Package for the project.
Jul 2023 Major works commenced on the project.
Jun 2025 The 2025-26 NSW Budget allocated $55 million to the M1 Pacific Motorway – Hexham Straight Upgrade in FY2025-26.
Feb 2026 The NSW Government announced that the project had been completed and commenced operations.
Estimated Total Cost
(2025)
Sector
Road
Procurement approach
Alliance |
Location
New South Wales |
Resources
Tender notices
2022/03/25