The proposed 100-megawatt / 1,080-megawatt hour Kingswood Battery Energy Storage System (BESS) is located approximately six kilometres southeast from Tamworth.
The project is proposed by Iberdrola.
Key Dates
| Oct 2023 | Project Announcement |
| 2026 | Expected Construction Commencement |
| 2027 | Expected Construction Completion |
Procurement
| Procuring Agency: | Iberdrola |
PROJECT HISTORY
| Oct 2023 | Iberdrola submitted a Scoping Report to the NSW Department of Planning and Environment, requesting the Secretary's Environmental Assessment Requirements (SEARs). The Scoping Report set out the proposed projects scope of a 500 MW / 1,000 MWh battery to be delivered across two stages. SEARs were subsequently issued for the project in October. |
| Jul 2024 | The project's Environmental Impact Statement (EIS) was placed on public exhibition by the NSW Department of Planning and Environment, with consultation closing on 15 August. The EIS updated the project's proposed scope, which is expected to comprise a single 270 MW / 1,080 MWh battery. |
| Oct 2025 | Iberdrola submitted a second amendment report to the NSW Major Planning Portal, outlining revisions to the project layout and construction timeframe. |
| Feb 2026 | ASL awarded Long-Term Energy Service Agreements to the project, along with five other long-duration storage projects under tender round six of the NSW Electricity Infrastructure Roadmap. The six projects have a combined capacity of 1.17 gigawatts and 12 gigawatt hours. The announcement also confirmed the project's expected capacity was revised to 100 MW / 1,080 MWh. |
Sector
Energy
Procurement approach
Unconfirmed |
Location
New South Wales |
Resources