The upgraded transit corridor will connect Liverpool to the new Bradfield city centre, enabling connections from Bradfield to WSI airport via Sydney Metro Western Sydney Airport.
The Liverpool to Airport Transit Corridor will be approximately 8.1km, comprising:
- 5.9 km along Fifteenth Avenue (between Devonshire Road and Cowpasture Road)
- 2.2 km along Hoxton Park Road (between Cowpasture Road and Banks Road).
Key Dates
| Jan 2025 | Project Announcement |
| Feb 2026 | ROIs Open |
| May 2026 | ROIs Close |
| Jun 2027 | Expected Construction Commencement |
| Jun 2031 | Expected Construction Completion |
Funding contributions
| Federal Government | |
| NSW Government |
Procurement
| Procuring Agency: | Transport for NSW |
| Procurement note: | The project will be delivered through a two-phase procurement process. |
| Related contracts: |
PROJECT HISTORY
| Mar 2018 | The NSW Government released the Greater Sydney Services and Infrastructure Plan which nominates the Hoxton Park Road and Fifteenth Avenue corridor as a rapid bus link. |
| Jun 2024 | The NSW 2024-25 Budget allocated $50 million for planning for the Liverpool to Airport Transit Corridor, including $4 million allocated in FY2024-25. |
| Jan 2025 | The Federal and NSW Governments announced a $1 billion upgrade to Fifteenth Avenue, linking Liverpool and Western Sydney International (WSI) airport, in Western Sydney. The project will be jointly funded on a 50:50 basis. |
| Aug 2025 | Transport for NSW awarded WSP the contract for concept design of the project. |
| Feb 2026 | Transport for NSW opened Registration of Interest for Stage One of the project. Stage One is expected to include 6 kilometres of road widening between Devonshire Road and Cowpasture Road. Stage Two, including delivery of a parallel bus transit-way, is not included in the contract scope. |
Estimated Total Cost
(2025)
Sector
Road
Procurement approach
Design and Construct (D&C) |