The Nerriga BESS is a 600-megawatt / 2.4-gigawatt hour Battery Energy Storage System proposed by North Harbour Clean Energy. The project is expected to connect to the existing Transgrid 330 kilovolt Capital Wind Farm to Kangaroo Valley transmission line.
Key Dates
| Jun 2028 | Expected Construction Commencement |
| Dec 2029 | Expected Construction Completion |
Procurement
| Procuring Agency: | North Harbour Clean Energy |
PROJECT HISTORY
| Apr 2025 | The NSW Department of Planning, Housing and Infrastructure issued SEARs for the project. |
| Mar 2026 | North Harbour Clean Energy submitted a scoping report and request for SEARs to the NSW Major Project Portal for the Nerriga BESS. |
Estimated Total Cost
(2026)
Sector
Energy
Procurement approach
Unconfirmed |
Location
New South Wales |