The Royal Perth Hospital Emergency Depatrment Redevelopment is a proposed package of works comprising the delivery of a six-story tower at the existing Royal Perth Hospital S block, to replace the existing Emergency Department.
The scope of the project includes delivery of:
- a six-story clinical tower,
- car parking area,
- expanded two level Emergency Department with new Ambulance bays,
- a dedicated Cardiac Investigation Unit and Cardiac Care Unit,
- a dedicated Dialysis unit,
- a Sub-Acute Cardiology Ward and a Renal Inpatient Ward,
- two Acute Medical Unit Wards, and
- provisions for future helipad.
Key Dates
| Nov 2025 | RFP Open |
| Dec 2025 | RFP Close |
| Jan 2026 | Preferred Bidder Selection |
| Jun 2026 | Construction Commencement |
Funding contributions
| WA Government | |
|
Funding from the project is sourced from the $1.5 billion Building Hospitals Fund |
|
Procurement
| Procuring Agency: | Department of Housing and Works |
| Successful Tenderer: | Lendlease |
| Procurement note: | The project will be delivered via a two-phase Alliance contract model following selection of the preferred proponent; Phase One, comprising design development and early construction work, and Phase Two, comprising design finalisation and main works construction. |
PROJECT HISTORY
| Jun 2025 | The 2025-26 Western Australian Budget allocated $5 million for preliminary studies and master planning for the Royal Perth Hospital. |
| Nov 2025 | The Western Australia Government confirmed that funding from the project would be sourced from the $1.5 billion Building Hospitals Fund. |
| Nov 2025 | The Western Australian Government called for Request for Proposals for an alliance contract for delivery of the project. Submissions Close 9 December. |
| Jan 2026 | Lendlease were selected as preferred alliance partners for the project. |
| Jun 2026 | Main works construction commenced on the project. |
Estimated Total Cost
(2026)
Sector
Social
Procurement approach
Alliance |
Location
Western Australia |