The Kwinana Bulk Terminal Redevelopment - Marine Infrastructure project will see the delivery of marine side infrasructure works required as part of the broader Westport - Kwinana Bulk Terminal redevelopment. The Marine Infrastructure project comprises works across five seperable packages, including:
- Package One - design and procurement of longer lead times
- Package Two - marine construction, including delivery of a two-berth wharf and associated infrastructure
- Package Three - civil construction, including seawall revetments, a 1.4 kilometre access causeway and drainage
- Package Four - dradging of berth pockets and turning basin, and
- Package Five - handover and commissioning
Westport has indicated that Package Four (Dredging) is an optional works package that may be procured seperatley.
Key Dates
| Jul 2026 | EOIs Open |
| Jun 2027 | Expected Contract Award |
| Apr 2028 | Expected Construction Commencement |
| Aug 2029 | Expected Construction Completion |
Procurement
| Procuring Agency: | Westport |
PROJECT HISTORY
| Jul 2026 | Westport called for Expressions of Interest (EOIs) for the Kwinana Bulk Terminal Redevelopment - Marine Infrastructure Project. The scope of works, to be delivered under a Design and Construct contract, comprises a two-berth wharf, an approach jetty and transfer platform, seawall revetments and a reclaimed access causeway, with the dredging component of the marine works offered as an optional package within this EOI process. EOIs close 13 August. |
Sector
Other Transport
Procurement approach
Design and Construct (D&C) |
Location
Western Australia |