Airside Civil and Pavement Works package comprises the construction of:
- a 3,700-metre runway
- access and exit taxiways and four rapid exit taxiways (RET) pavements
- parallel taxiway pavements and aircraft isolation pad
- engine run-up bay
- aeronautical ground lighting (AGL) for CAT IIIB operations
- perimeter roads and airside roads,and
- security fencing, including civil works provisioning for services such as CCTV, lighting, communications and power.
At the stage of procurement commencement, the package did not include terminal apron, apron roads, aviation fuel distribution, rescue and firefighting facilites or navigational aids.
Key Dates
Feb 2020 | ROIs Open |
Sep 2021 | Contract Award |
Mar 2022 | Construction Commencement |
Jun 2025 | Construction Completion |
2026 | Expected Airport Operations Commencement |
Procurement
Procuring Agency: | Western Sydney Airport |
Successful Tenderer: | CPB Contractors and ACCIONA joint venture |
Related contracts: |
PROJECT HISTORY
Aug 2018 | Western Sydney Airport announced that Main Works Package One would be split in to three sub packages to allow more businesses to be involved in the project. This resulted in Main Works Packages 1A, 1B and 1C. Package 1A and 1B has since been consolidated to a single Bulk Bulk Earthworks Package while 1C is now known as the Airside Civil and Pavement Works package. |
Feb 2020 | Western Sydney Airport invited Registration of Interest (ROI) for Airside Civil and Pavement Works package, closing on 24 February. Expression of Interest (EOI) process was expected to begin in June, with contract award expected in the third quarter of 2021. |
Sep 2021 | Western Sydney Airport awarded the design and construct contract for the Airside Civil and Pavement Works package to a CPB Contractors and ACCIONA joint venture. Major construction was expected to begin in 2022. |
Sep 2021 | WSP were appointed as the Independent Certifier on the Airside Civil and Pavement Works package. |
Mar 2022 | Main works construction commenced. |
Jan 2024 | Construction completed on the 3,700 metre runway section of the project. |
Jun 2025 | CPB Contractors announced the Airside Civil and Pavement Works project was complete, with testing to commence ahead of the airport's expected operations commencement in 2026. |
Sector
Other Transport
Procurement approach
Traditional Procurement |
Location
New South Wales |
Resources